Roof completed 15/01/10 and bricks started 28/01/10
Ok so I have been away and busy and I haven't updated my blog again! On the 15/01/10 our roof was fully tiled and today they started our bricks our frame was wrapped last week - Here are some photos
Building Contract: 30.08.09
Land Settled: 08.10.09
Building permit: 21.10.09
Site Start: 12.11.09
Site plumbed: 17.11.09
Slab 23.11.09
Frame started 04.12.09
Bricks for garage started 07.12.09
Frame completed 18.12.09
Gutters started 04.01.10
Roof completed 15.01.10
Frame wrapped 19.01.10
Bricks for house started 28.01.10
Lock up 05.03.10
Plastered 19.03.10
Kitchen in 21.04.10
Fixing completed 30.04.10
Painting Started 03.05.10
Painting Finished 20.05.10
PCI:28.05.10
Carpet layed: 01.06.10
Boards Polished: 03.06.10
Handover : 11.06.10!!!