With 3 days to go I thought I might post one last building update with some pics for you all! Some of these photos were taken through the windows so excuse the reflection : )
Building Contract: 30.08.09
Land Settled: 08.10.09
Building permit: 21.10.09
Site Start: 12.11.09
Site plumbed: 17.11.09
Slab 23.11.09
Frame started 04.12.09
Bricks for garage started 07.12.09
Frame completed 18.12.09
Gutters started 04.01.10
Roof completed 15.01.10
Frame wrapped 19.01.10
Bricks for house started 28.01.10
Lock up 05.03.10
Plastered 19.03.10
Kitchen in 21.04.10
Fixing completed 30.04.10
Painting Started 03.05.10
Painting Finished 20.05.10
PCI:28.05.10
Carpet layed: 01.06.10
Boards Polished: 03.06.10
Handover : 11.06.10!!!