Well we had the day off work today and we decided to drive by the block around lunchtime and saw the builders doing our slab! Yay so exciting - now comes the 1st invoice oh well : )
Building Contract: 30.08.09
Land Settled: 08.10.09
Building permit: 21.10.09
Site Start: 12.11.09
Site plumbed: 17.11.09
Slab 23.11.09
Frame started 04.12.09
Bricks for garage started 07.12.09
Frame completed 18.12.09
Gutters started 04.01.10
Roof completed 15.01.10
Frame wrapped 19.01.10
Bricks for house started 28.01.10
Lock up 05.03.10
Plastered 19.03.10
Kitchen in 21.04.10
Fixing completed 30.04.10
Painting Started 03.05.10
Painting Finished 20.05.10
PCI:28.05.10
Carpet layed: 01.06.10
Boards Polished: 03.06.10
Handover : 11.06.10!!!
Yes I saw it this morning on my drive by to school. Looks very nice.
ReplyDeleteNice Slab, its always good to see how big your place is on the block and yes that bill is a decent one!!!
ReplyDelete