Over the last couple of days we have had our bricks delivered and our frame got delivered on tuesday but no work has been done on the block since the slab was poured. Here r sum pics of our bricks and frame. Cheers Ryan
Building Contract: 30.08.09
Land Settled: 08.10.09
Building permit: 21.10.09
Site Start: 12.11.09
Site plumbed: 17.11.09
Slab 23.11.09
Frame started 04.12.09
Bricks for garage started 07.12.09
Frame completed 18.12.09
Gutters started 04.01.10
Roof completed 15.01.10
Frame wrapped 19.01.10
Bricks for house started 28.01.10
Lock up 05.03.10
Plastered 19.03.10
Kitchen in 21.04.10
Fixing completed 30.04.10
Painting Started 03.05.10
Painting Finished 20.05.10
PCI:28.05.10
Carpet layed: 01.06.10
Boards Polished: 03.06.10
Handover : 11.06.10!!!