Roof completed 15/01/10 and bricks started 28/01/10
















Ok so I have been away and busy and I haven't updated my blog again! On the 15/01/10 our roof was fully tiled and today they started our bricks our frame was wrapped last week - Here are some photos










Monday, January 4, 2010

Frame completed 18.12.09!







Well Well Well! It has been a while since I have posted on here! My frame was completed ages ago and I have been very slack! I have been enjoying my xmas and new year break : )



I went to my block today and I was very supprised to see they had started the guttering which I was extremely supprised by as they are supposed to be on holidays but hey I dont mind : )



Well here are the photos:






Wednesday, December 9, 2009

Frame started 04.12.09 and bricks 07.12.09!!
























Well well well! It has been a while and I must admit I haven't kept my blog up to date. Now I will be honest and say that is because I cannot be bothered to wait for the photos to upload : D

So what has been happening in Mooroolbark you say? We have a frame!!! Yay wahoooo! Well half a frame no roof yet but that was delivered today - check out the photos : ))))

Thursday, December 3, 2009

Deliverys Deliverys 3/12/09

















Over the last couple of days we have had our bricks delivered and our frame got delivered on tuesday but no work has been done on the block since the slab was poured. Here r sum pics of our bricks and frame. Cheers Ryan

Monday, November 23, 2009

Slab!!! 23.11.09




Well we had the day off work today and we decided to drive by the block around lunchtime and saw the builders doing our slab! Yay so exciting - now comes the 1st invoice oh well : )

Friday, November 20, 2009




The rio has been fitted today so the boxing up for the slab is complete. So im guessing when we get a few hot days in a row they will pour the slab so it has time to cure (its raining at the moment).
The builders toilet has also been delivered this is my highlight of the week........






Wednesday, November 18, 2009

Pipes 18.11.09
















Ok so now this is up to date finally! I drove past tonight and we have pipes and looks like we are getting close to a slab! Yay dunno if they will work tommorow as it is going to be hot hot hot! But you never know could have a slab on Monday or Tuesday I reakon!