Monday, March 29, 2010

Plastered!!! 19.03.10
















Again I am behind on my blog. The house was completely plastered just over a week ago - Yes I am very slack! I promise not to be when my kitchen goes in! I swear! Well our house was fully plastered by 19.03.10 took about 4 days and last week we had our bricks cleaned and some square things on the pipes in the ground for the down pipes to be installed later and that is all! Not a very great week last week for progress and lets see how this next 2 weeks go with easter : )










Thanks for looking....

Friday, March 12, 2010

Lock up!!!! 05.03.10
















It has been a while since I posted anything on here. Mainly because we had about 3 1/2 weeks of no progress and it only took the builders 2 weeks to get my house to lock up. This week our insulation was put in and the Spa bath and shower bases. The carpenter also made our cavity slider door for the ensuite. The plaster has also now been delivered and the house is ready to be plastered next week - Well lets hope....

Thursday, January 28, 2010

Roof completed 15/01/10 and bricks started 28/01/10
















Ok so I have been away and busy and I haven't updated my blog again! On the 15/01/10 our roof was fully tiled and today they started our bricks our frame was wrapped last week - Here are some photos










Monday, January 4, 2010

Frame completed 18.12.09!







Well Well Well! It has been a while since I have posted on here! My frame was completed ages ago and I have been very slack! I have been enjoying my xmas and new year break : )



I went to my block today and I was very supprised to see they had started the guttering which I was extremely supprised by as they are supposed to be on holidays but hey I dont mind : )



Well here are the photos:






Wednesday, December 9, 2009

Frame started 04.12.09 and bricks 07.12.09!!
























Well well well! It has been a while and I must admit I haven't kept my blog up to date. Now I will be honest and say that is because I cannot be bothered to wait for the photos to upload : D

So what has been happening in Mooroolbark you say? We have a frame!!! Yay wahoooo! Well half a frame no roof yet but that was delivered today - check out the photos : ))))

Thursday, December 3, 2009

Deliverys Deliverys 3/12/09

















Over the last couple of days we have had our bricks delivered and our frame got delivered on tuesday but no work has been done on the block since the slab was poured. Here r sum pics of our bricks and frame. Cheers Ryan

Monday, November 23, 2009

Slab!!! 23.11.09




Well we had the day off work today and we decided to drive by the block around lunchtime and saw the builders doing our slab! Yay so exciting - now comes the 1st invoice oh well : )